E Project — Cross-Department 5M1E

E-PROJECT · Plant 3 + Kempas Temporary Yard cross-department 5M1E readiness

PUBLIC VIEW / 公开页面WEB VERSION / 网页版

E Project — 5M1E Readiness Dashboard

Plant 3 + Kempas Temporary Yard cross-department 5M1E readiness · QAC · PE · Production · Warehouse · EHS · 2026-08-26

Overall Readiness / 总体准备度

28%

95 checklist items

Open Items / 未结案

81

Requires owner & next action

Critical Open / 关键未结

16

Click to view in Master Checklist / 点击查看

Overdue / 逾期

0

Click to view in Master Checklist / 点击查看

Department Readiness / 部门准备度
DepartmentReadinessOpenCriticalRAG
QAC
55%
100Amber/黄
PE
0%
60Red/红
Production
0%
150Red/红
Warehouse
0%
250Red/红
EHS
55%
2516Red/红
5M1E Readiness Summary / 分类准备度
5M1EReadinessOpenCriticalRAG
Man/人
16%
214Red/红
Machine/机
20%
154Red/红
Material/料
37%
121Red/红
Method/法
25%
124Red/红
Measurement/测
35%
101Red/红
Environment/环
44%
112Red/红
Readiness by Department (%)
55%
QAC
0%
PE
0%
Production
0%
Warehouse
55%
EHS
Readiness by 5M1E (%)
16%
Man
20%
Machine
37%
Material
25%
Method
35%
Measurement
44%
Environment
Material Fulfilment Summary / 物料到货汇总

Shanghai HQ Material / 上海总部物料

0%
0Line Items / 品项
0Requested / 申请
0Received / 入库
0Outstanding / 未入库

DCM Purchase-request Material / DCM抬头申购物料

0%
0Line Items / 品项
0Requested / 申请
0Received / 入库
0Outstanding / 未入库
Management Decisions and Escalations / 管理层决策与升级事项
No.Decision RequiredRecommendationOwnerApprovalTarget
1EHS manpower coverageRestart recruitment; minimum experienced EHS/OSH Coordinator, registered SHO preferredManagement / HRPending/待批准Before start-up
2Simultaneous high-risk work at two sitesStagger or suspend one site when qualified EHS coverage is unavailableManagement / Production / EHSPending/待批准Before start-up
324-hour look-ahead notificationSubmit next-day high-risk work plan at a fixed daily cut-off; no notification, no workProduction / EHSPending/待批准Before start-up
4Temporary yard emergency and scheduled-waste responsibilityConfirm ERP, First Aider and waste responsibility in writingManagement / EHS / WarehousePending/待批准Before start-up